Current Projects

What are we currently working on?

We encourage you to check this page often as we update the projects currently being worked on around the garden condo III community.


We have put together a chart for easy reference as to when we expect to complete the following roofing, siding and dripline projects over the course of the next six months.

Click to download - 2018 Project Chart -- Driplines, Roofs and Siding.


Dripline Replacement Schedule

Our dripline replacement program continues. Our dripline replacement program will continue each month this year with a scheduled completion of June, 2018. Our current schedule for 2018 (subject to change) is as follows:

    January -- Units 374-385 -- start 1/10/18 -- end 1/19/2018 -- duration = 9 days
    February -- Units 246-253 -- start 2/6/18 -- end 2/11/2018 -- duration = 5 days
    February -- Units 254-261 -- start 2/20/18 -- end 2/25/2018 -- duration = 5 days
    March -- Units 280-289 -- start 3/6/18 -- end 3/11/2018 -- duration = 5 days
    March -- Units 290-299 -- start 3/20/18 -- end 3/25/2018 -- duration = 5 days
    April -- Units 472-477 -- start 4/10/18 -- end 4/15/2018 -- duration = 5 days
    April -- Units 362-373 -- start 4/24/18 -- end 4/29/2018 -- duration = 5 days
    May -- Units 386-393 -- start 5/8/18 -- end 5/13/2018 -- duration = 5 days
    May -- Units 394-401 -- start 5/22/18 -- end 5/27/2018 -- duration = 5 days
    June -- Units 350-361 -- start 6/12/18 -- end 6/17/2018 -- duration = 5 days
~~~

Siding Replacement Project

Our siding replacement program continues. We have begun the task of replacing the lower sections of the walls that the outside of units and are deteriorating due to water damage. This project will be completed over a series of months. Our current schedule for 2018 (subject to change) is as follows:

    January -- Units 410-417 -- start 1/15/18 -- end 1/18/2018 -- duration = 3 days
    February -- Units 290-293 -- start 2/15/18 -- end 2/18/2018 -- duration = 3 days
    March -- Units 238-245 -- start 3/15/18 -- end 3/18/2018 -- duration = 3 days
    March -- Units 338-341 -- start 3/20/18 -- end 3/23/2018 -- duration = 3 days
    April -- Units 282-289 -- start 4/15/18 -- end 4/18/2018 -- duration = 3 days
    April -- Units 374-375 -- start 4/20/18 -- end 4/23/2018 -- duration = 3 days
    May -- Units 272-277 -- start 5/15/18 -- end 5/18/2018 -- duration = 3 days
    May -- Units 346-349 -- start 5/20/18 -- end 5/23/2018 -- duration = 3 days
    June -- Units 386-393 -- start 6/15/18 -- end 6/18/2018 -- duration = 3 days
    June -- Units 430-435 -- start 6/20/18 -- end 6/23/2018 -- duration = 3 days
    July -- Units 464-471 -- start 7/15/18 -- end 7/18/2018 -- duration = 3 days
    July -- Units 456-457 -- start 7/19/18 -- end 7/22/2018 -- duration = 3 days
~~~

Roof Replacement Project

Our roof replacement program is going extremely well and we continue to accelerate the completion which is now scheduled for April of this year. Below is the anticipated schedule:

    January -- Units 448-453 -- start 1/10/18 -- end 1/19/2018 -- duration = 9 days
    January -- Units 472-475 -- start 1/24/18 -- end 1/29/2018 -- duration = 5 days
    February -- Units 476-477 -- start 2/5/18 -- end 2/9/2018 -- duration = 4 days
    February -- Units 478-481 -- start 2/12/18 -- end 2/17/2018 -- duration = 6 days
    February -- Units 482-485 -- start 2/19/18 -- end 2/24/2018 -- duration = 5 days
    March -- Units 493-496 -- start 3/5/18 -- end 3/10/2018 -- duration = 5 days
    March -- Units 497-500 -- start 3/19/18 -- end 3/24/2018 -- duration = 5 days
    April -- Units 501-504 -- start 4/2/18 -- end 4/7/2018 -- duration = 5 days
    April -- Units 505-508 -- start 4/16/18 -- end 4/21/2018 -- duration = 5 days
    April -- Golf Cart Storage - East and West -- start 4/26/18 -- end 4/29/2018 -- duration = 3 days